Module Assembly Status
Foundation Set
Ground Floor Modules
Upper Floor Stacking
Inter-Module Connections
Envelope Sealing
⚙ Modular / Volumetric Construction — HVHZ

Modular Building Wind Load Requirements in Miami-Dade County

Modular and volumetric construction in Miami-Dade's High Velocity Hurricane Zone (HVHZ) requires design for 180 MPH ultimate wind speeds per ASCE 7-22, with inter-module connections engineered to transfer shear forces of 15–40 kips per joint, module-to-foundation anchorage resisting net uplift exceeding 20 kips per anchor, and Miami-Dade Product Control approval for every prefabricated component entering the HVHZ. Each module must withstand transportation loads, crane-lift wind restrictions of 20–25 MPH, and permanent in-service hurricane forces without relying on adjacent modules for stability until all connections are completed and inspected.

⚠️ Critical Assembly Requirement

Every modular unit must be independently stable under design wind loads before inter-module connections are completed. Temporary bracing capable of resisting 180 MPH forces is required during the setting sequence — a single unsecured module in Miami-Dade can become a projectile weighing 30,000–60,000 lbs.

0
HVHZ Design Wind Speed
0
Max Inter-Module Shear Force
0
Crane Lift Wind Limit
0
Typical Module Weight

Modular Assembly & Wind Load Force Diagram

Interactive view of a 3-story modular stack showing inter-module connections, tie-down anchor points, and wind pressure distribution on the assembled structure

Module A1 — 12×60 ft
Module A2 — 12×60 ft
Module B1 — 12×60 ft
Module B2 — 12×60 ft
Module C1 — 12×60 ft
Module C2 — 12×60 ft
Vertical Tie: 22 kip uplift
Vertical Tie: 22 kip uplift
Vertical Tie: 18 kip uplift
Vertical Tie: 18 kip uplift
Lateral Shear: 32 kip
Lateral Shear: 28 kip
Lateral Shear: 24 kip
Anchor: 25 kip tension
Anchor: 25 kip tension
Anchor: 25 kip tension
Anchor: 25 kip tension
qh = 68 psf
qh = 60 psf
qh = 52 psf
🛫 Max lift: 25 MPH

ASCE 7-22 Wind Load Provisions for Modular Buildings

How the Main Wind Force Resisting System (MWFRS) and Components & Cladding (C&C) chapters apply to volumetric modular construction

MWFRS Design Under Chapter 27

Modular buildings in Miami-Dade's HVHZ must be analyzed as complete assembled structures under ASCE 7-22 Chapter 27 for enclosed or partially enclosed rigid buildings. The 180 MPH ultimate wind speed (Vult) with Exposure Category C—the default for much of coastal Miami-Dade—produces velocity pressures ranging from 52.4 psf at 15-foot mean roof height to 68.3 psf at 60 feet. These pressures are applied using the directional procedure with wind from all directions to determine the controlling MWFRS load case.

For modular buildings, a critical distinction arises: the structure is not monolithic. Wind forces must transfer through discrete inter-module connections rather than continuous structural members. The engineer must verify that the summation of connection capacities at each floor level equals or exceeds the story shear demands calculated from the MWFRS analysis. For a typical 3-story modular hotel in Miami-Dade with a 120-foot windward face, the base shear under 180 MPH winds reaches approximately 85–120 kips depending on building proportions and exposure.

  • Risk Category II buildings: Importance factor Iw = 1.0
  • Risk Category III (hotels with 300+ occupants): Iw = 1.0 but higher minimum requirements per HVHZ
  • Risk Category IV (essential facilities): Iw = 1.0 with Vult = 180 MPH (already governs in HVHZ)
  • Topographic factor Kzt = 1.0 for flat terrain typical of Miami-Dade
  • Ground elevation factor Ke = 1.0 at sea level

C&C Pressures on Module Envelopes

Each modular unit arrives at the site with its exterior cladding, windows, and weatherproofing already installed during factory fabrication. These Components and Cladding (C&C) elements must resist the zone-specific pressures defined in ASCE 7-22 Chapter 30 based on their effective wind area and position on the assembled building. The factory engineer must account for the module's eventual position—a corner module at the top floor experiences vastly different C&C pressures than a mid-span ground-floor module.

For a 3-story modular building with 33-foot mean roof height at 180 MPH in Exposure C, the C&C design pressures for wall cladding elements reach:

  • Wall Zone 4 (interior): -32 psf to +27 psf for 20 sq ft tributary area
  • Wall Zone 5 (corners): -48 psf to +27 psf for 10 sq ft tributary area
  • Roof Zone 1 (interior): -54 psf for flat or low-slope roofs
  • Roof Zone 2 (perimeter): -88 psf requiring enhanced fastening
  • Roof Zone 3 (corners): -108 psf — the most demanding zone
  • These pressures include internal pressure coefficients for enclosed buildings (GCpi = ±0.18)

Inter-Module Connection Design for Hurricane Forces

Bolted steel plates, welded embeds, and proprietary bracket systems engineered for 180 MPH wind-induced forces at every module joint

🔩

Bolted Steel Plate Connections

The most common inter-module connection method uses steel plates with high-strength A325 or A490 bolts. At each vertical connection point between stacked modules, a top plate welded to the lower module's ceiling frame aligns with a bottom plate welded to the upper module's floor frame. Typical configurations use 4–8 bolts per connection, with 0.75-inch to 1.25-inch diameter bolts depending on the force demand. For Miami-Dade's 180 MPH design, corner connections on a 3-story building commonly require eight 1-inch A490 bolts to resist combined 22-kip uplift and 15-kip shear.

8x A490 bolts per corner joint

Welded Embed Plates

Modules with concrete floor and ceiling systems use welded embed plates cast into the concrete during factory fabrication. Nelson studs or headed anchors transfer forces between the embed plate and the concrete substrate. The embed plate is sized to resist the bearing and punching shear stresses from the concentrated bolt loads. For 180 MPH connections, embed plates of 0.5-inch to 0.75-inch A36 steel with four to six 0.75-inch headed studs provide the anchorage capacity. Field welding between modules can supplement bolted connections but requires AWS D1.1 certified welders and HVHZ-approved inspection.

0.75" A36 plates with headed studs
🔗

Horizontal Diaphragm Transfer

Wind loads acting on the building face must transfer through floor and roof diaphragms to the lateral-force-resisting elements. In modular buildings, the diaphragm is discontinuous at module joints. Engineers must design positive connections—typically steel angles or plates bolted across the joint—to ensure diaphragm continuity. The connection must transfer the in-plane shear stress, which at 180 MPH can reach 200–400 plf along the module joint depending on the building's aspect ratio and number of modules per floor. Failure to achieve diaphragm continuity can result in progressive collapse under lateral wind loads.

200-400 plf diaphragm shear demand

Module-to-Foundation Anchorage

Ground-floor modules must be anchored to the concrete foundation to resist the full overturning moment, base shear, and net uplift from the 180 MPH wind loading on the complete stacked assembly above. Anchor bolt embedment into reinforced concrete piers follows ACI 318 Chapter 17 design provisions for concrete breakout, pullout, and side-face blowout. For a 3-story modular building with 24-foot modules, each foundation anchor point typically requires 1.25-inch diameter F1554 Grade 55 anchor bolts with 18–24 inches of embedment. Net uplift at windward corners can exceed 25 kips per anchor under the controlling load combination of 0.9D + 1.0W.

1.25" anchors, 18-24" embedment

Transportation Loads & Crane Lifting Restrictions

Wind engineering challenges unique to modular construction: from factory to foundation in Miami-Dade's unpredictable wind climate

Highway Transportation Wind Loads

Modular units must survive highway transportation from the manufacturing facility to the Miami-Dade construction site, often traveling 200–1,000+ miles on flatbed trailers. During transit at 55–65 MPH, modules experience apparent wind speeds that combine vehicle velocity with ambient crosswinds. A 15 MPH crosswind at 60 MPH vehicle speed produces an effective resultant wind speed of approximately 62 MPH, generating 15–25 psf pressure on the module's exposed 400–800 square-foot side face.

Transport tie-down systems must be engineered independently from the permanent structural connections. Chain binders rated at 4–8 times the module weight secure units to step-deck or flatbed trailers at four to eight attachment points. The Florida Department of Transportation requires oversize load permits for modules exceeding 8.5 feet wide, 13.5 feet tall, or 53 feet long. Temporary bracing installed inside modules during transport—typically steel angles or compression struts spanning the module diagonally—prevents racking deformation from dynamic road loads and must be designed by a licensed engineer.

Modules manufactured outside Florida must cross state lines with appropriate permits and pilot car escorts. Routing through coastal areas with bridge clearance restrictions and weight limits adds complexity. Rain infiltration during transport can damage factory-installed finishes; shrink-wrap or tarping of partially enclosed modules is standard practice but adds wind resistance during transit.

Crane Operations & Wind Restrictions

Crane lifting of modular units is the most wind-sensitive phase of construction. A typical volumetric module weighing 30,000–60,000 pounds presents a sail area of 400–800 square feet during the lift—a dangerous combination of mass and wind susceptibility. Most crane manufacturers limit operations to sustained wind speeds of 20–25 MPH at the boom tip, and this threshold can be reduced to 15 MPH for modules with large sail areas or long pick radii.

In Miami-Dade, where afternoon sea-breeze convergence zones and summer thunderstorm outflow boundaries produce rapid wind speed changes, crane operations require continuous anemometer monitoring at boom height. The project's critical lift plan, reviewed by the crane operator's engineer and the project structural engineer, must include:

  • Abort criteria: sustained winds exceeding 20 MPH or gusts above 30 MPH
  • Module tie-down procedures for partially completed lift sequences
  • Temporary bracing installation sequence for each module immediately after placement
  • Contingency plans for securing modules if weather deteriorates mid-sequence
  • Early morning scheduling (6–10 AM) when wind speeds are typically lowest in South Florida
  • Lightning proximity protocols: operations suspended when lightning is within 10 miles

Each module must achieve temporary stability immediately upon placement. The gap between crane release and permanent connection completion is the highest-risk period for modular construction in the HVHZ. Temporary bolting or clamping at a minimum of four points per module is mandatory before the crane releases the rigging.

Factory QC vs. Field Inspection & Product Control

Navigating Miami-Dade's dual inspection regime: factory certification plus field verification for every modular building component

Factory Inspection & Certification

Modular units manufactured for Miami-Dade HVHZ must be produced in factories inspected by a Miami-Dade approved quality assurance entity or a state-approved third-party agency. The factory inspection program verifies that structural steel connections match engineering drawings, welding conforms to AWS D1.1, concrete strength meets specified f'c values (typically 5,000–6,000 psi for modules), and all envelope components carry valid product approvals. Each module receives a serialized data plate confirming compliance.

Third-party factory audit required for HVHZ

Miami-Dade Product Control NOA

The Product Control Division requires a Notice of Acceptance (NOA) for modular building systems installed in the HVHZ. The NOA application encompasses the structural frame, inter-module connections, exterior cladding, windows, doors, and roofing. Testing per Florida TAS protocols—TAS 201 (large missile impact at 50 fps), TAS 202 (cyclic pressure), and TAS 203 (static pressure)—must demonstrate compliance at the 180 MPH design wind speed. The NOA specifies approved configurations and prohibits field modifications without engineering review.

TAS 201/202/203 testing required

Field Connection Inspection

After module placement, every inter-module connection must be inspected by a Miami-Dade licensed special inspector. The inspection verifies bolt torque values (typically 150–200 ft-lbs for 1-inch A325 bolts), weld quality for field-welded connections per AWS D1.1, anchor bolt embedment depth and concrete condition, and connection geometry matching the approved shop drawings. Threshold inspections per FBC Section 1709 apply to modular buildings exceeding three stories, requiring the structural engineer of record to provide periodic field observations.

Special inspection per FBC 1709

Diaphragm & Progressive Collapse Review

Before certificate of occupancy, the structural engineer of record must certify that all diaphragm connections between modules are complete and that the progressive collapse analysis assumptions have been verified in the field. For buildings exceeding 4 stories, the Miami-Dade building official may require a project-specific progressive collapse analysis per the GSA alternate path method demonstrating that removal of any single ground-floor module does not trigger cascading failure of the structure above. This analysis must account for the 180 MPH wind load as a concurrent lateral force during the notional removal scenario.

GSA alternate path for 4+ stories

Design Wind Pressures by Module Position

Velocity pressures and net design loads at different heights for modular buildings in Miami-Dade HVHZ, Exposure C

Floor Level Height (ft) qz (psf) MWFRS Windward (psf) C&C Wall Zone 5 (psf) C&C Roof Zone 3 (psf)
Ground (Module A) 0–12 ft 52.4 +22.8 -48.2
2nd Floor (Module B) 12–24 ft 58.1 +25.3 -53.4
3rd Floor (Module C) 24–36 ft 62.8 +27.3 -57.8
Roof Level 36 ft (mean) 65.4 -108.3

FBC 2023 Modular Building Certification

The Florida Building Code 2023, Section 458 (Manufactured Buildings and Transportable Structures), establishes the regulatory framework for modular construction in Florida. Modular buildings must be certified by a state-approved inspection agency that audits the manufacturing facility and certifies each module's compliance with the FBC structural, fire, plumbing, mechanical, and electrical requirements.

For HVHZ installations, the FBC requires additional compliance with the High Velocity Hurricane Zone provisions of Chapter 44 (FBC Building) and the Miami-Dade County Specific Amendments. These amendments impose stricter requirements for connection testing, envelope component approval, and special inspection that exceed the base FBC requirements. A modular building certified for non-HVHZ locations in Florida cannot be installed in Miami-Dade without meeting these additional HVHZ provisions.

The state insignia program issues a decal for each certified module confirming compliance with the FBC edition in effect at the time of manufacture. However, Miami-Dade requires that the insignia approval specifically includes HVHZ compliance—a standard Florida insignia without HVHZ designation is insufficient for permit approval in Miami-Dade County.

Progressive Collapse Prevention

Progressive collapse in modular buildings occurs when the failure of one module or connection triggers cascading failures through the structure. This vulnerability is heightened during hurricanes when simultaneous wind pressures, wind-borne debris impact, and uplift forces act on the building. For modular buildings in Miami-Dade's HVHZ, the structural engineer must address progressive collapse through redundant load paths designed into the inter-module connection system.

Strategies employed in HVHZ modular buildings include:

  • Continuous vertical tie rods extending from foundation to roof, independent of individual module connections, providing a minimum tension capacity of 2 kips per linear foot of building perimeter
  • Horizontal tie connections at every floor level with minimum capacity of 1.5 kips per linear foot distributed across all module joints
  • Corner module connections enhanced to 150% of calculated demand to account for combined uplift and lateral pressure concentration
  • Catenary action provisions allowing floor systems to span over a removed support with deflection limited to one story height
  • GSA alternate path analysis for buildings exceeding 4 stories, demonstrating structural stability with any single module notionally removed

Modular Construction in Miami-Dade County

Real-world applications of volumetric modular building systems in the HVHZ, from student housing to hospitality

🏨

Modular Hotel Projects

Several hospitality brands have deployed modular construction for hotel projects in South Florida, attracted by the 30–50% schedule reduction compared to conventional construction. A typical 120-key, 4-story modular hotel uses approximately 130–150 modules, each containing a completed guest room with bathroom, HVAC, and finishes. In Miami-Dade, these projects require enhanced steel corner frames with 0.5-inch gusset plates at every column-to-beam intersection to resist the 180 MPH wind loads without relying on interior partition walls for lateral resistance.

130-150 modules per hotel
🏫

Student Housing Complexes

University dormitory projects in Miami-Dade have adopted modular construction to meet tight academic-calendar deadlines—buildings must be ready for fall semester occupancy regardless of South Florida's summer hurricane season. Typical 4–6 story student housing buildings use modules sized at 12×56 feet or 14×60 feet, each containing one or two student bedrooms with shared or private bathrooms. The repetitive room layout is ideal for modular fabrication, and the steel-framed modules stack efficiently. Wind engineering challenges include the corridor modules that have large openings on both ends, creating partially enclosed conditions with higher internal pressure coefficients (GCpi = ±0.55) until the building envelope is sealed.

Partially enclosed GCpi = ±0.55 during construction
🏡

Workforce & Affordable Housing

Miami-Dade's affordable housing shortage has driven interest in modular construction for workforce housing developments. These projects typically range from 3–5 stories and use concrete-framed or hybrid steel-concrete modules to meet fire-resistance rating requirements for Type I or Type II construction. The cost savings from factory production (estimated at 15–25% versus conventional) help offset the premium associated with HVHZ-compliant connections and product approvals. Module-to-module fire barriers at every joint require fire-rated sealants tested to ASTM E119 for the required 1–2 hour rating, adding complexity to the inter-module connection design beyond structural requirements alone.

15-25% cost savings vs. conventional
📖

Healthcare & Laboratory Modules

Modular construction has expanded into healthcare facilities in South Florida, including urgent care clinics, laboratory buildings, and medical office buildings. These Risk Category III structures in Miami-Dade must resist the same 180 MPH wind speed as standard buildings but face additional requirements for continuous operation during and after hurricanes. The structural engineer must verify that inter-module deflections under wind load do not compromise the operability of sensitive medical equipment. Vibration criteria for laboratory modules—typically VC-A or VC-B per AISC Design Guide 11—add stiffness requirements beyond those governed by wind alone.

Risk Category III: essential facility requirements
🔨

Construction Sequencing Challenges

The construction sequence for modular buildings in Miami-Dade must account for hurricane season (June 1 through November 30), during which partially assembled structures are vulnerable to tropical storm and hurricane-force winds. The building department may require a hurricane preparedness plan demonstrating that the structure at any intermediate stage of module placement can resist the design wind loads. This often requires installing temporary bracing systems—steel X-braces or strongback columns—at the end of each day's module placement sequence to stabilize the partially completed building overnight.

June 1 – Nov 30 hurricane season planning

MEP Coordination at Module Joints

Mechanical, electrical, and plumbing (MEP) systems that cross module boundaries present waterproofing challenges at every joint. Plumbing drain lines, conduit runs, and HVAC ducts must connect at precise alignment points between modules while maintaining the structural integrity of the connection and the weather-tightness of the building envelope. In the HVHZ, where wind-driven rain pressures can exceed 8 psf per ASCE 7-22 Appendix D, every penetration through the module joint requires tested and approved flashing details. Typical practice uses pre-installed stub-outs that telescope or flex-connect at the module joint, sealed with HVHZ-approved sealants and covered with metal counter-flashing.

Wind-driven rain: 8+ psf at joints

Diaphragm Action Across Module Joints

Engineering the discontinuous floor plane to behave as a continuous diaphragm for lateral wind load distribution

The floor system of a modular building consists of individual module floor diaphragms separated by joints at every module boundary. For a building with two modules side-by-side and three stories high, each floor level has a longitudinal joint running the full length of the building. Under lateral wind loads, these diaphragms must act as horizontal beams, collecting wind pressure from the windward wall and distributing it to the lateral-force-resisting elements on either side of the building.

In conventional construction, the floor diaphragm is continuous plywood or concrete, providing inherent in-plane shear transfer. In modular construction, the engineer must design explicit connections across the module joint to achieve diaphragm continuity. The shear flow across the joint can be calculated as V·Q/(I·t) for elastic behavior or simplified as the total story shear divided by the diaphragm length for a rigid diaphragm assumption. For a 120-foot-long modular building under 180 MPH wind loads in Miami-Dade, the diaphragm shear at the module joint reaches 300–500 plf, requiring steel angle connections at 12–24 inches on center with two 0.75-inch A325 bolts per angle.

ASCE 7-22 Section 12.3.1 requires that diaphragm flexibility be evaluated—modular floor systems with bolted connections at the joints may exhibit semi-rigid behavior rather than the fully rigid assumption used in many analyses. The structural engineer should verify that the connection stiffness provides adequate force distribution by comparing the midspan diaphragm deflection to the average inter-story drift. If the diaphragm deflection exceeds twice the average story drift, a flexible diaphragm analysis distributing wind loads based on tributary area rather than relative stiffness may govern the design of individual lateral-force-resisting elements.

Modular Wind Load FAQ

Answers to common questions about wind engineering for modular and volumetric construction in the HVHZ

Modular buildings in Miami-Dade County must be designed for a 180 MPH ultimate (Vult) design wind speed per ASCE 7-22 and the Florida Building Code 2023. This applies to the entire High Velocity Hurricane Zone (HVHZ) encompassing all of Miami-Dade County. The 180 MPH requirement governs the design of each individual module's structural frame, all inter-module connections, the module-to-foundation anchorage system, and every component and cladding element attached to the modules. This wind speed produces velocity pressures ranging from 52 psf at ground level to over 70 psf at 60-foot heights for Exposure C conditions, generating substantially higher forces than the 150–160 MPH zones found in most other Florida coastal counties.
Inter-module connections in modular buildings must transfer wind-induced shear, tension, and compression forces across joints that did not exist during factory fabrication and testing. Unlike conventional steel or concrete connections designed into a monolithic structure, modular connections must be completed in the field under variable conditions while achieving the same structural capacity as factory-welded joints. Typical inter-module connections use bolted steel plates with 4–8 high-strength A325 or A490 bolts per connection point, welded embed plates cast into concrete module floors and ceilings, or proprietary interlocking steel bracket systems. For 180 MPH wind loads in Miami-Dade, each vertical inter-module connection must resist 15–40 kips of horizontal shear and 10–25 kips of uplift tension depending on the module's position in the building stack and its tributary area. Connection design must also account for construction tolerances of ±0.5 inches that accumulate across multiple stacked modules.
Crane lifting operations for modular construction are typically restricted to sustained wind speeds of 20–25 MPH at the crane boom tip, though specific limits depend on the crane manufacturer's load charts, module weight, pick radius, and lift height. A typical volumetric module weighing 30,000–60,000 pounds presents a large sail area of 400–800 square feet during lifting, making it extremely sensitive to wind gusts. In Miami-Dade, where afternoon thunderstorm outflow boundaries can produce sudden wind gusts exceeding 40 MPH with minimal warning, crane operations require continuous wind speed monitoring at boom height using anemometers. Most modular construction projects in South Florida schedule critical lifts during early morning hours between 6 AM and 10 AM when wind speeds are typically lowest. The project's crane lift plan must include abort criteria, module tie-down procedures for partially completed lifts, and contingency plans for rapidly securing modules if weather deteriorates during the setting sequence.
Yes, modular building systems in Miami-Dade HVHZ require product approval through the Miami-Dade County Product Control Division. The modular manufacturer must obtain either a Notice of Acceptance (NOA) covering the complete modular system including structural frame, inter-module connections, exterior cladding, windows, doors, and roofing, or alternatively obtain individual NOAs for each component that interfaces with the building envelope. The NOA application requires full-scale or component-level testing per Florida Testing Application Standards (TAS) including TAS 201 for large missile impact, TAS 202 for cyclic pressure, and TAS 203 for uniform static pressure for all envelope components. Factory inspection of the manufacturing facility by a Miami-Dade approved quality assurance entity is also required. The manufacturer's quality control program must demonstrate that every module produced maintains the same structural capacity and envelope integrity as the tested prototype specimens.
Progressive collapse prevention in stacked modular buildings requires that the removal of any single module or the failure of any individual inter-module connection does not trigger cascading structural failure of adjacent modules. For wind load design in Miami-Dade HVHZ, this means designing redundant load paths so that wind forces can redistribute through alternative connections if one connection point is compromised. Strategies include providing continuous vertical tie elements (steel rods or cables) through the full building height independent of individual module connections, designing horizontal diaphragm connections at each floor level to distribute lateral loads to multiple vertical load paths, and ensuring that corner modules have enhanced connections since they experience the highest combined wind pressures. ASCE 7-22 Section 1.4 requires structural integrity provisions, and for modular buildings exceeding 4 stories in Miami-Dade, a project-specific progressive collapse analysis per the General Services Administration (GSA) alternate path method is often required by the building official as a condition of permit approval.
Modular building units must be designed for transportation wind loads encountered during highway delivery from the manufacturing facility to the construction site. During transport on flatbed trailers at highway speeds of 55–65 MPH, modules experience apparent wind speeds that combine vehicle speed with ambient crosswind, producing effective wind pressures of 15–25 psf on exposed surfaces. ASCE 7-22 does not directly address transportation loads, so engineers typically apply the load combinations from the AISC Design Guide 29 for modular construction or use first-principles aerodynamic analysis. For modules manufactured outside South Florida and shipped to Miami-Dade, the transport route may expose partially enclosed modules to rain infiltration that could compromise interior finishes. Transport tie-down systems using chains rated at 4–8 times the module weight secure modules to trailers, and oversize load permits from the Florida Department of Transportation are required for modules exceeding 8.5 feet wide, 13.5 feet tall, or 53 feet long. Temporary bracing installed for transport is different from permanent wind bracing and must be engineered separately.

Get MWFRS Wind Loads for Your Modular Project

Calculate accurate MWFRS and C&C wind pressures for modular buildings in Miami-Dade's HVHZ. Determine inter-module connection forces, foundation anchorage demands, and envelope component pressures.